Solar Street Light Installation

1. Installation of solar panels

Note: The positive and negative poles of the battery plate should not be reversed

2. Installation of LED lamp head

Note: The positive and negative poles of the lamp head should not be reversed Note: The screw must be tightened

3. Installation of accumulators

4. Connection of controller

Connection sequence: light source->accumulator->battery plate

Step 1: On the positive and negative pole controller of the light source, take care that the positive and negative poles are not reversed, and wrap them with water-resistant adhesive.

Step 2: Connect the positive pole of the positive battery plate of the accumulator to the first red line of the controller and wrap it with water-resistant adhesive.

Step 3: Connect the negative pole of the accumulator to the controller and wrap it with water-resistant adhesive.At this time, the idle light of the controller is on, wait about a minute, the discharge light is on, and the light source is on when the discharge light is on.

Step 4: When the light source is lit, connect the negative poles of the battery plate and wrap them with water-resistant adhesive.Within five minutes, the light source will automatically go out and the controller will enter the charging state.

5. Connection of individual parts

6. Lifting

Before lifting the A lamp pole, check that the fasteners in each part are firm, the lamp head is installed correctly, and the solar panel is facing (directly south) correctly.

B Lock expansion screw of flange parts after hoisting installation.Open the controller door on the lamp pole and hang the controller on the inner arm of the lamp pole.